The Impact of Federal Permitting on Clean Energy Development
The federal permitting process is delaying, downsizing, and deterring energy projects – at a moment when electricity demand is growing faster than any point in recent memory.
Crux surveyed 50 renewable energy developers and permitting professionals to quantify what federal permitting is actually costing the market. The findings have direct implications for how projects get financed, sited, and built.
Inside the whitepaper, you'll find:
- Why 80% of developers are intentionally siting projects to avoid triggering federal permitting requirements — and what that means for capital deployment
- How federal permitting contributed to roughly 11 GW of impacted capacity across survey respondents alone in the last year
- The cost burden by the numbers: 100% of developers reported higher project costs, with 58% citing a 6–10% increase in total project costs
- What developers actually want — and why predictability, not weaker environmental protections, is the dominant ask
Download the whitepaper to see what the data reveals about the future of energy project development.


Download the report
What’s inside the report
Every developer surveyed had projects materially affected by federal permitting in the last year — roughly 11 GW of capacity across respondents alone.
More than 80% of developers surveyed intentionally site projects to avoid triggering federal permitting, so the true cost of permitting is systematically undercounted.
Federal permitting increased development costs for every respondent, and 58% reported a 6–10% increase in total project costs.
Projects delayed by federal permitting are held up more than six months on average, pushing back the delivery of new energy supply.